# Airtable WORKDAY: deadlines, weekends and holidays
- URL: https://airtables.net/airtable-workday/
- Published: 2026-11-10T17:59:13.000Z
- Updated: 2026-11-23T17:27:38.000Z
- Description: Calculate working-day deadlines with an explicit holiday calendar and distinguish dates after a start from a task that includes day one.
- Author: Emma Hayes
- Tags: Formulas

Use `WORKDAY({Start date}, 5)` to calculate a date five working days after an Airtable date, skipping Saturday and Sunday. Supply a comma-separated ISO date list as the third argument to skip office closures too. If you already have both dates and want a count, use `WORKDAY_DIFF`; its answer is a number.

I'd define whether the starting date counts as day one before building dependent milestones. That choice can change a correct formula's deadline by a working day.

## Create a deadline that skips weekends

The function is available on all plans. Owner or Creator permissions are required to add or configure its Formula field, as Airtable's [date-functions guide](https://support.airtable.com/articles/5452033436-working-with-date-functions-in-airtable?ref=airtables.net) explains. A formula calculation does not itself use an automation run; sending a reminder is a separate operation.

1. Create a **Date** field named **Start date**.
2. Add a **Formula** field named **Due date** and paste the expression below.
3. Open **Formatting** and choose a date display. Keep the source and result on the same time-zone convention.
4. Save the field and check existing records as well as your sample record.

```
IF(
  {Start date},
  WORKDAY({Start date}, 5),
  BLANK()
)
```

The output is a calculated date, or blank when Start date is missing. These examples use date-only values with consistent GMT formatting and no excluded holidays:

| Start date             | Expected Due date | Reason                              |
| ---------------------- | ----------------- | ----------------------------------- |
| Monday, April 6, 2026  | Monday, April 13  | Five weekdays after Monday          |
| Empty                  | Blank             | No deadline for an unfinished input |
| Friday, April 10, 2026 | Friday, April 17  | Saturday and Sunday are skipped     |

[![Airtable WORKDAY formula adds five working days from the Start date](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-create.webp)](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-create.webp?ref=airtables.net)

Use WORKDAY for a weekday deadline and leave the output blank until there is a start date. [View full size](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-create.webp?ref=airtables.net).

## Choose WORKDAY, DATEADD or WORKDAY\_DIFF

```
WORKDAY(startDate, numDays, [holidays])
WORKDAY_DIFF(startDate, endDate, [holidays])
```

The brackets mark an optional argument; do not type those brackets into your formula. Neither function takes a unit argument such as “days.” Airtable's [function reference](https://support.airtable.com/articles/7330071120-airtable-formula-field-functions-reference?ref=airtables.net) documents their argument order and the holiday-list format.

| Your question                                        | Choose         | Output |
| ---------------------------------------------------- | -------------- | ------ |
| What date is five working days after receipt?        | WORKDAY        | Date   |
| What date is five calendar days later?               | DATEADD        | Date   |
| How many eligible working dates fall in this range?  | WORKDAY\_DIFF  | Number |
| How many actual hours passed between two timestamps? | DATETIME\_DIFF | Number |

[DATEADD](https://airtables.net/airtable-dateadd/) does not skip weekends. [DATETIME\_DIFF](https://airtables.net/airtable-datetime-diff/) does not subtract the hours when an office was closed. Choose the calendar rule first, then the function.

## Exclude holidays and office closures

The third argument is a string of dates in **YYYY-MM-DD** format. For this example, assume the office closes on Monday, April 13, 2026:

```
IF(
  {Start date},
  WORKDAY({Start date}, 1, "2026-04-13"),
  BLANK()
)
```

One working day after Friday, April 10 is now Tuesday, April 14\. Without that closure, it is Monday, April 13\. Five working days after the same Friday becomes Monday, April 20.

For several closures, use a list such as `"2026-04-13,2026-04-20"`. WORKDAY does not fetch a country's holiday calendar. Include observed holidays, regional closures and the correct year's dates when they apply to the team. “Spring break” or “Christmas” is a name, not a usable date.

### Read the list from a field

Create a text field called **Holidays** containing the ISO list. Use the two-argument version when that field is empty:

```
IF(
  {Start date},
  IF(
    {Holidays},
    WORKDAY({Start date}, 5, {Holidays}),
    WORKDAY({Start date}, 5)
  ),
  BLANK()
)
```

Keep only the dates and commas in Holidays. A space-only entry is not a meaningful calendar. If records follow different regional calendars, give each the appropriate list rather than combining every office's closures.

### Build a reusable list from linked closure records

For a small base, a **Closures** table can store each closure once. Each task links to the closure records that apply to its calendar:

1. In Closures, add a Date field called **Closure date**.
2. Add a Formula field called **Holiday ISO** with the formula below.
3. In Tasks, add **Link to another record** pointing to Closures. Link the applicable dates, including the following year when a task crosses December.
4. Add a Rollup field named **Holidays**. Choose that link and Holiday ISO, then use the aggregation below.

```
IF(
  {Closure date},
  DATETIME_FORMAT({Closure date}, "YYYY-MM-DD"),
  BLANK()
)
```

```
ARRAYJOIN(ARRAYUNIQUE(ARRAYCOMPACT(values)), ",")
```

The first expression belongs in Closures; the second belongs in the Tasks rollup's aggregation box. It removes empty values and duplicates, then joins the ISO strings with commas. These are documented [array aggregation functions](https://support.airtable.com/articles/7330071120-airtable-formula-field-functions-reference?ref=airtables.net). Check that the resulting Holidays cell reads, for example, `2026-04-13,2026-04-20` before passing it to WORKDAY.

A new row in Closures is not automatically linked to every task. Assigning the applicable calendar remains part of this model. For many tasks, maintain calendars by team or region and bring each calendar's prepared list into its tasks; avoid manually retyping the same dates into every record. The [lookup and rollup guide](https://airtables.net/airtable-lookup-rollup-fields/) explains how related values become a list or an aggregate.

[![Airtable WORKDAY output skips April 13 when the Holidays text lists that date](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-closure-text.webp)](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-closure-text.webp?ref=airtables.net)

One workday after Friday normally lands on Monday. With Monday in the holiday list, the deadline moves to Tuesday. [View full size](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-closure-text.webp?ref=airtables.net).

## Decide when day one begins

“Five working days after receipt” excludes the receipt date. “A five-day task, with the start counted as day one” includes an eligible starting date. With Friday, April 10 as the start and no closures, those deadlines are April 17 and April 16 respectively.

If every Start date is already a working date, the inclusive five-day version is:

```
IF({Start date}, WORKDAY({Start date}, 4), BLANK())
```

That shortcut needs a separate decision when a request arrives on Saturday or on a holiday. To start on the first eligible working date *on or after* receipt, create **First working date**:

```
IF(
  {Received date},
  IF(
    {Holidays},
    WORKDAY(DATEADD({Received date}, -1, "days"), 1, {Holidays}),
    WORKDAY(DATEADD({Received date}, -1, "days"), 1)
  ),
  BLANK()
)
```

Received date must be a date-only field here. Moving back one calendar day and then forward one eligible workday keeps an eligible receipt date, but advances a weekend or closure date. If Holidays contains April 13, a Saturday, April 11 receipt starts Tuesday, April 14.

For a five-day task including that first working date, calculate four more workdays from it:

```
IF(
  {First working date},
  IF(
    {Holidays},
    WORKDAY({First working date}, 4, {Holidays}),
    WORKDAY({First working date}, 4)
  ),
  BLANK()
)
```

The Saturday receipt above therefore finishes Monday, April 20: April 14, 15, 16, 17 and 20 are its five working dates. A one-day task finishes on First working date itself. Define any afternoon cutoff separately; this date-only rule does not decide whether a 5:30 PM receipt counts as today's work.

## Use a variable offset, including zero and negative values

Add a Number field named **Workday offset**. The following formula accepts whole numbers, uses the record's Holidays list, and explicitly defines zero as “keep Start date unchanged,” even if that date is a weekend:

```
IF(
  AND(
    {Start date},
    LEN({Workday offset} & "") > 0,
    MOD({Workday offset}, 1) = 0
  ),
  IF(
    {Workday offset} = 0,
    {Start date},
    IF(
      {Holidays},
      WORKDAY({Start date}, {Workday offset}, {Holidays}),
      WORKDAY({Start date}, {Workday offset})
    )
  ),
  BLANK()
)
```

The nonempty check keeps zero distinct from a missing number; MOD rejects fractional days under this whole-day policy. It does not silently round a task's estimate. A Duration field belongs elsewhere: Airtable [stores Duration values in seconds](https://support.airtable.com/articles/8465756875-duration-fields-in-airtable?ref=airtables.net), so a displayed 8:00 is not eight workdays.

Negative offsets schedule backwards. With April 13 excluded, two working days before Wednesday, April 15 is Friday, April 10: Tuesday is the first date counted backwards, Monday is closed, and Friday is the second. The core expression is `WORKDAY({Due date}, -2, {Holidays})`; omit its third argument if the list is empty. Negative counts are also used in this [back-scheduling discussion](https://community.airtable.com/formulas-10/formula-add-7-days-excluding-sundays-and-holidays-34450?ref=airtables.net).

If an offset comes from a lookup, resolve it to one numeric value before using this recipe. A cell that displays one number may still contain an array; do not join several milestone offsets into a string and hope WORKDAY selects one.

For a dependent timeline, keep a planned deadline separate from a stored **Actual finish**. A later task can read the appropriate completion date, but WORKDAY does not record when a status changed. Airtable's [status-timestamp workflow](https://support.airtable.com/articles/9267771468-use-automations-to-timestamp-status-updates?ref=airtables.net) stores that event through an automation. TODAY would keep moving after completion, so it is the wrong anchor for a permanent completion date.

[![Airtable working-day deadline handles a negative offset, zero and an empty offset](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-variable-zero.webp)](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-variable-zero.webp?ref=airtables.net)

A negative offset moves to an earlier workday. Zero retains the starting date under this formula. [View full size](https://storage.ghost.io/c/a9/2c/a92c670f-47cf-4c4a-afab-8582761151cb/content/images/2026/11/airtable-guide-workday-variable-zero.webp?ref=airtables.net).

## Count working dates with WORKDAY\_DIFF

Use Start date followed by End date. This version leaves incomplete or reversed ranges blank; keep a separate review flag if an End date before Start date is an input error:

```
IF(
  AND({Start date}, {End date}),
  IF(
    IS_BEFORE({End date}, {Start date}),
    BLANK(),
    IF(
      {Holidays},
      WORKDAY_DIFF({Start date}, {End date}, {Holidays}),
      WORKDAY_DIFF({Start date}, {End date})
    )
  ),
  BLANK()
)
```

The result is a number of eligible dates, including both ends of a forward range when those dates are working dates. Airtable's [WORKDAY\_DIFF launch explanation](https://community.airtable.com/formulas-10/number-of-working-days-between-two-dates-without-weekends-33744?ref=airtables.net) explicitly describes this inclusive behavior.

| Date-only range                             | No closures | April 13 excluded |
| ------------------------------------------- | ----------- | ----------------- |
| Friday, April 10 through Monday, April 13   | 2           | 1                 |
| Friday, April 10 through that same Friday   | 1           | 1                 |
| Saturday, April 11 through Sunday, April 12 | 0           | 0                 |
| Monday, April 13 through that same Monday   | 1           | 0                 |

This is why WORKDAY\_DIFF is not a simple inverse of WORKDAY. Five working days *after* an eligible start gives an interval containing six eligible dates when you include the start. Do not remove one indiscriminately from every WORKDAY\_DIFF result: a Saturday start contributes nothing to remove.

Multiplying the count by eight gives an assumed eight hours for each eligible date. It does not measure staffed time. Friday at 4 PM to Monday at 9 AM contains one staffed hour under a 9–5 schedule with no closures: Friday's 4–5 PM hour. Counting staffed time requires clipping timestamps to opening hours, weekends, holidays and any breaks. Neither WORKDAY\_DIFF nor elapsed DATETIME\_DIFF alone expresses that calendar.

## Handle calendar-day deadlines and custom workweeks separately

Four calendar days after Friday, April 10 is Tuesday, April 14\. Four working days after that Friday is Thursday, April 16 without closures. These are different policies.

If the rule is “add calendar days, then move an ineligible result forward,” first calculate **Target date** with DATEADD. Apply the First working date pattern above to Target date instead of Received date. For example, Friday plus one calendar day gives Saturday; the roll-forward step gives Monday, or Tuesday when Monday is in Holidays. Do not replace the whole calculation with WORKDAY and assume it means the same thing.

WORKDAY's documented arguments have no custom weekend mask. A holiday list can exclude more dates, but it cannot make Saturday a normal working date. For Sunday-only weekends, Friday/Saturday weekends or rotating shifts, use a calendar model that explicitly marks each eligible date; this function's Monday–Friday assumptions cannot represent that schedule.

## Fix a Sunday display without moving the deadline

If a result appears to land on Sunday, inspect the source date and formula field's **Edit field → Formatting** settings. Show hidden times where needed, and compare the common-time-zone option. A timestamp near midnight may display as the previous date in another zone.

Airtable's [time-zone reference](https://support.airtable.com/articles/7730575816-timezones-and-locales-in-airtable?ref=airtables.net) explains GMT storage and local display. In a [milestone troubleshooting thread](https://community.airtable.com/formulas-10/workday-formula-returning-the-wrong-dates-35048?ref=airtables.net), the asker confirmed that matching GMT settings fixed apparent weekend dates. Adding a compensating day changes the value used by later milestones too.

Keep WORKDAY's output as a date for a timeline or another calculation. DATETIME\_FORMAT returns text; use the field's Formatting settings for a readable date, and put an email label in a separate field. If the formula will not save, check for a stray “days” argument, missing comma or unmatched parenthesis before changing the calendar.

Before connecting a reminder or dependent task, compare an ordinary date, an empty input, a Friday boundary and a closure date in the source field, result field and destination action. Use the same Holidays list in every stage that follows the same calendar.